Oakton College is continuing campus improvement projects including those outlined in our recently approved facilities master plan, which will result in transformed spaces that create an optimal learning and working environment for students and employees.
Check back often as this page will help minimize operational disruptions and keep you informed of our progress.
Latest Update: Jan. 28, 2025
Des Plaines Library Learning Commons |
|
Stakeholder(s): |
Library, Learning Center, Center for Teaching Innovation, Math Labs (STEM), TRIO, IT Help Desk |
Percent Complete: |
3% |
Project Start: |
|
Project Completion: |
|
The Project is out to bid and a construction schedule will be established once a contractor has been awarded the project. The Library and Learning Center have temporarily relocated to TenHoeve rooms. The Testing Center and Access and Disability Resource Center (ADRC) will move at a later date. |
Door and Hardware Replacement |
|
Percent Complete: |
10% |
Project Start: |
TBD |
Project Completion: |
TBD |
Kluber Architects is working on construction documents for phase 1, which entails repairs and replacement to exterior doors across both campuses. Construction dates will be established upon completion of construction documents and bidding process. |
Landscape Master Plan Project |
|
Percent Complete: |
95% |
Project Start: |
10/23/2023 |
Project Completion: |
TBD |
Work is progressing across both campuses. The contractor is working on completing punch list items (weather permitting). Some plantings will be added or replaced in the spring when weather allows. A new railing is being installed along the north side of Lake Oakton at the Des Plaines Campus. |
Student Affairs, Information Technology and Access and Disability Resource Center (ADRC) Office Renovations (Des Plaines Floor 2) |
|
Stakeholder(s): |
Office of Student Affairs, Oakton IT, ADRC, Testing Center |
Percent Complete: |
7% |
Project Start: |
|
Project Completion: |
|
Phase 1 projects for the IT Hub, Testing Center, and ADRC are under construction. Phase 2 projects for the Office of Student Affairs, Workforce Development, and bookstore are in design. |