Oakton College is continuing campus improvement projects including those outlined in our recently approved facilities master plan, which will result in transformed spaces that create an optimal learning and working environment for students and employees.
Check back often as this page will help minimize operational disruptions and keep you informed of our progress.
Latest Update: Feb. 24, 2025
Des Plaines Library Learning Commons |
|
Stakeholder(s): |
Library, Learning Center, Center for Teaching Innovation, Math Labs (STEM), TRIO, IT Help Desk |
Percent Complete: |
3% |
Project Start: |
|
Project Completion: |
|
Bidding for the project has been completed and a construction schedule will be established once a contractor has been awarded the project. |
Door and Hardware Replacement |
|
Percent Complete: |
10% |
Project Start: |
TBD |
Project Completion: |
TBD |
Kluber Architects is working with facilities to complete the construction documents for the exterior door and hardware replacements/ repairs. The project is expected to go out to bid in the spring. |
Landscape Master Plan Project |
|
Percent Complete: |
97% |
Project Start: |
10/23/2023 |
Project Completion: |
TBD |
Work is progressing across both campuses. The contractor is working on completing punch list items (weather permitting). Some plantings will be added or replaced in the spring when weather allows. |
Student Affairs, Information Technology and Access and Disability Resource Center (ADRC) Office Renovations (Des Plaines Floor 2) |
|
Stakeholder(s): |
Office of Student Affairs, Oakton IT, ADRC, Testing Center |
Percent Complete: |
7% |
Project Start: |
|
Project Completion: |
|
Phase 1 projects for the IT Hub, Testing Center, and ADRC are under construction. Phase 2 projects for the Office of Student Affairs, Workforce Development, and bookstore are in design. |