Construction

Appears to be an image of Oakly waving outside at Oakton College's Des Plaines campus.
  • The Des Plaines campus Library and Learning Center have moved to their temporary location in the TenHoeve wing (1600 rooms). The TenHoeve Rooms at the Des Plaines campus will be unavailable for events and meetings until Dec. 31, 2025.
  • The Division of Student Affairs has temporarily re-located to Room 2817.
Rendering of the new Oakton Library Learning Commons.

Des Plaines Library Learning Commons 

Stakeholder(s):

Library, Learning Center, Center for Teaching Innovation, Math Labs (STEM), TRIO, IT Help Desk

Percent Complete:

 3%

Project Start:

 

Project Completion:

 

Bidding for the project has been completed and a construction schedule will be established once a contractor has been awarded the project.

The Library and Learning Center have temporarily relocated to Ten Hoeve rooms. The Testing Center is scheduled to move on March 10. Testing Center check-in will be in Ten Hoeve room 1610, and the Testing Room will be located in 1605. The ADRC office is scheduled to move to room 2548 on March 5.

An image of the new door and hardware replacement at Oakton College.

Door and Hardware Replacement

Percent Complete:

10%

Project Start:

TBD

Project Completion:

TBD

Kluber Architects is working with facilities to complete the construction documents for the exterior door and hardware replacements/ repairs. The project is expected to go out to bid in the spring.

An image of the master construction plan at Oakton College.

Landscape Master Plan Project

Percent Complete:

97%

Project Start:

10/23/2023

Project Completion:

TBD

Work is progressing across both campuses. The contractor is working on completing punch list items (weather permitting). Some plantings will be added or replaced in the spring when weather allows. 

An image of the Oakton College Leaf on a grey b

Student Affairs, Information Technology and Access and Disability Resource Center (ADRC) Office Renovations (Des Plaines Floor 2)

Stakeholder(s):

Office of Student Affairs, Oakton IT, ADRC, Testing Center

Percent Complete:

7%

Project Start:

Project Completion:

Phase 1 projects for the IT Hub, Testing Center, and ADRC are under construction. Phase 2 projects for the Office of Student Affairs, Workforce Development, and bookstore are in design.